How the concrete calculator works
Concrete is ordered by volume. Enter the dimensions of the slab, beam, footing, wall or column and the calculator multiplies them to get the volume, then adds the waste allowance you choose to cover spillage, uneven sub-grade and over-excavation.
Results are shown in cubic yards (imperial) or cubic metres (metric), together with the number of 60 lb and 80 lb pre-mix bags for small jobs. For anything over about one cubic yard, ordering ready-mix delivered by truck is normally cheaper and faster than mixing bags.
For walls and slabs, add openings — windows, doors or stair openings — and their volume is deducted at the full thickness before the waste allowance is added. The optional mix breakdown uses the dry-volume method: the volume including waste is multiplied by 1.54 and split by the mix ratio, with cement shown in 50 kg bags (metric) or 94 lb bags (imperial).
The optional rebar estimate counts bars for the shape you picked — top and bottom layers both ways for slabs, both faces for walls, 4 longitudinal bars plus stirrups for beams and footings, and 4 longitudinal bars plus circular ties for round columns. It shows the total bar length and weight before waste and with waste applied, the number of standard-length bars to order (40 ft imperial, 12 m metric), and the ties or stirrups. For walls and slabs the bar length is reduced in proportion to the opening area, since opening positions are not entered. This is a quantity estimate only, not a structural design tool.
The optional formwork estimate works out the contact area — the surface the formwork touches — for the shape you picked: both faces of a wall less the openings, the edge of a slab including the edges of any openings, three sides of a beam, the sides of a footing, and the circumference of a round column. It also counts the standard plywood sheets to buy (4 by 8 ft, or 1220 by 2440 mm), rounded up. This is a quantity estimate only, not a structural design tool.
Formulas used
- Slab = length x width x thickness
- Beam / footing = length x width x depth (x number of beams)
- Wall = length x height x thickness
- Round column = pi x (diameter / 2)^2 x height (x number of columns)
- Cubic yards = cubic feet / 27, then add waste
- Openings (wall / slab) = width x height x thickness (x count), deducted before waste
- Mix: dry volume = wet volume x 1.54, split by the mix ratio; cement = dry volume share x 1440 kg/m³
- Rebar: bars = length / spacing + 1 per row; slab = 2 layers x both directions, wall = 2 faces x vertical + horizontal, beam/footing = 4 longitudinal bars + stirrups, column = 4 longitudinal bars + circular ties; weight = length x bar weight (metric kg/m = diameter² / 162)
- Rebar with waste = exact length x (1 + waste); standard bars = length with waste / 40 ft (imperial) or 12 m (metric), rounded up
- Formwork: wall = 2 x length x height, less openings on both faces; slab = edge perimeter x thickness (including the edges of openings); beam = (2 x depth + width) x length (x number of beams); footing = perimeter x depth; round column = pi x diameter x height (x number of columns)
- Plywood sheets = formwork area / 32 sq ft (4 x 8 ft sheet), rounded up
Frequently asked questions
How much waste should I add to a concrete order?
Most contractors add 5 to 10 percent. Use 10 percent or more for footings dug in soil, irregular excavations or when the sub-base is not perfectly level.
How many bags of concrete make one cubic yard?
About 45 bags of 80 lb mix or 60 bags of 60 lb mix make one cubic yard. The calculator shows the bag count for your volume.
How thick should a concrete slab be?
Residential patios and walkways are typically 4 inches (100 mm). Driveways and garage floors are usually 5 to 6 inches (125 to 150 mm).
How do I deduct windows and doors from a concrete wall?
Add each opening under Openings — its width, height and how many there are. The volume is deducted at the full wall thickness before waste is added, since there is no waste on concrete never poured.
What mix ratio should I use?
1:2:4 (cement : sand : aggregate) is the common general-purpose mix for slabs, footings and walls. 1:1.5:3 is stronger for columns and beams, and 1:3:6 is a lean mix for blinding and mass concrete.
How much rebar do I need for a slab?
Tick “Show rebar estimate”, pick the bar size and the center-to-center spacing. A 20 by 10 ft slab at 12 in spacing with #4 bars needs about 860 ft of bar (about 574 lb) before waste, in top and bottom layers both ways. The calculator also counts the 40 ft (or 12 m) stock bars to order.
How much formwork do I need for a wall?
Tick “Show formwork estimate”. A 20 by 8 ft wall needs 320 sq ft of formwork (both faces), which is 10 sheets of 4 by 8 ft plywood. Openings are deducted on both faces.
Is this a structural design tool?
No. It estimates material quantity only. Have an engineer specify thickness, reinforcement and mix for structural work.